Determining an Accurate Estimate of a roject Completion Time Using Simulation

Authors: Aravind. M, Aravindhababu. V, Balamurugnan. K

Ask about this article

Abstract

Select any words in the title or abstract, or press this and choose a sentence.

The mean project completion time determined by the traditional PERT analysis is always an underestimate of the actual project completion time. This paper suggests an improved methodology to estimate the mean project completion time using simulation

Subjects

Engineering

Ask about this article

Answers come only from this article's title, abstract and keywords, each sentence pointing to where it comes from. Your question is sent to OpenAI to write the answer. Scholars Central does not store it.

Try:

Similar by topic

More from this journal

The newest in International Journal of Innovative Research in Science, Engineering and Technology.

All its articles

Conferences in this field

Upcoming conferences in this field.

Follow

New articles from what you follow go into your email digest, once you agree to alert emails.

  • JournalInternational Journal of Innovative Research in Science, Engineering and Technology
  • SubjectEngineering
  • BylineArticles whose byline prints “Aravind. M”
  • BylineArticles whose byline prints “Aravindhababu. V”
  • BylineArticles whose byline prints “Balamurugnan. K”

For authors and organisers

Publish, present and keep up with your field

Find the right journal for your paper and submit your manuscript.

Photo: Pexels